DOI: 10.1016/j.enpol.2021.112421
论文题名:
Exploring the link between project delays and cancelation rates in the U.S. rooftop solar industry
作者: Cook J.J.; Cruce J.; O'Shaughnessy E.; Ardani K.; Margolis R.
刊名: Energy Policy
ISSN: 03014215
出版年: 2021
卷: 156
语种: 英语
中文关键词: Cancellations ; Inspection ; Interconnection ; Permitting ; Solar ; Utilities
英文关键词: Risk assessment ; Solar power generation ; Surveys ; Cancelation ; Contract signature ; Interconnection ; Permitting ; Photovoltaics ; Project delays ; Solar ; Solar industries ; Systems operation ; Utility ; Inspection
英文摘要: About 1 in 10 rooftop solar photovoltaic (PV) customers who sign a contract to install a PV system cancel their contract before the system is installed. Although some cancelation risk is inherent in the solar industry, there may be ways to reduce cancelation volume, such as reducing project delays. Delays can occur at each stage of PV adoption processes, which take several weeks to months from contract signature to system operation. Using data from a recent survey of PV installers, we explore the factors that explain PV project delays and cancelations. The survey data suggest that PV adoptions take about 16 weeks, on average, from contract signature until system operation. Survey respondents consistently identified permitting, inspection, and interconnection (PII) processes as key drivers of project delays. Most respondents then suggested these PII-related delays increase contract cancelations. However, larger-scale installers report higher cancelation rates, and these installers rank changes in customer financial situations higher than PII-related delays as the main cause for cancelations. Most respondents also reported avoiding jurisdictions with particularly onerous PII requirements or charging more in these jurisdictions. On balance, the results provide a rationale for measures to streamline PII processes to reduce delays and potentially mitigate cancelation risk. © 2021 Elsevier Ltd
Citation statistics:
被引频次[WOS]:3   [查看WOS记录]     [查看WOS中相关记录]
资源类型: 期刊论文
标识符: http://119.78.100.158/handle/2HF3EXSE/167738
Appears in Collections:气候变化与战略

Files in This Item:

There are no files associated with this item.


作者单位: National Renewable Energy Laboratory, 15013 Denver West Parkway, GoldenCO 80401, United States; Clean Kilowatts, LLC, United States

Recommended Citation:
Cook J.J.,Cruce J.,O'Shaughnessy E.,et al. Exploring the link between project delays and cancelation rates in the U.S. rooftop solar industry[J]. Energy Policy,2021-01-01,156
Service
Recommend this item
Sava as my favorate item
Show this item's statistics
Export Endnote File
Google Scholar
Similar articles in Google Scholar
[Cook J.J.]'s Articles
[Cruce J.]'s Articles
[O'Shaughnessy E.]'s Articles
百度学术
Similar articles in Baidu Scholar
[Cook J.J.]'s Articles
[Cruce J.]'s Articles
[O'Shaughnessy E.]'s Articles
CSDL cross search
Similar articles in CSDL Cross Search
[Cook J.J.]‘s Articles
[Cruce J.]‘s Articles
[O'Shaughnessy E.]‘s Articles
Related Copyright Policies
Null
收藏/分享
所有评论 (0)
暂无评论
 

Items in IR are protected by copyright, with all rights reserved, unless otherwise indicated.